Goldhawk

Underground vault strengthening beneath London’s streets

London basement propping for a cellar and vault strengthening system
London basement propping for a cellar and vault strengthening system

Popular London venue, the Star is a very well established French Bistro during the day and specialist Gin Club at night. All of a sudden the venue discovered that its underground tasting rooms in the brick vaults were cracking and leaking. The evident damage and potential safety risk rendered these essential spaces unusable.

Buildings insurance claim underway

Propping was installed to prevent potential collapse as Goldhawk were brought in by the Insurers to assess the extent of the problem and design a solution.

Specialist vault strengthening

The Star’s arched brick vaults are located beneath Hollen Street roadway and are subject to full Highway loading. Assessment of the arches revealed that in their damaged state they were significantly understrength, and the road would need to be temporarily closed. Using Goldhawk’s own unique MARS system our team designed and installed a strengthening scheme suitable for each individual arch. This enabled the infrastructure team at FM Conway to carefully lift the street surfacing over the arch and apply a waterproof membrane before reinstating the paving and road make up.

Completion and results

The venue successfully returned to full use of the under-street vaults whilst the road above carries the weight of busy London Traffic. The cost-effective MARS solution prevented the need to carry out expensive, disruptive and time consuming reconstruction of their historic basement vaults and cellars.

The vault propping in place during the strengthening and repair

Propping the vault

Props were installed to support the arch during the completion of works.

Insurance repair to an underground brick vault and cellar

MARS system installation

A strengthening scheme was designed for each arch.

The Goldhawk team repairing the vault beneath the pavement in London

Specialist team

Goldhawk’s team installed the unique MARS strengthening system.

The cementitious mortar applied to the vault strengthening project in London

Carefully finished

The process of completion.

making good the brickwork after the vault strengthening MARS system as been installed

Sealed and weatherproof

Each archway was carefully finished ready to reopen the vaults.

Assessing the pavement for the cellar and basement vault repair at Great Chapel Street, London

Roadworks completed

The subterranean vaults are now protected from the weight of modern London traffic.